Ninth in a series tracking Pegula Ice Arena construction every few weeks (February 7, 2012 / March 27, 2012 / April 10, 2012 / May 20, 2012 / June 15, 2012 / June 27, 2012 / July 20, 2012 / August 21, 2012).
So, funny story. Apparently word got back to Mortenson Construction that I trespassed on their site for the June 15th and July 20th versions of this post. As a result, word got back to me that they would press charges if I did it again.
I'm going to spare you the tearful apology because, to be honest, I'm not really sorry. I understand the issues from their point of view (mostly related to insurance and liability, I'm sure), and I don't really blame them for protecting themselves, but I'm a harmless blogger who just wanted a closer look. I'm not going to sue if I hurt myself doing something stupid, and I certainly didn't disrupt anything, nor did I keep any souvenirs. In short, I got some great pictures to share with all of you and didn't harm myself or anyone else in any way.
Maybe they should invite media to come on to the site once in a while. Just a thought. I really do hope that they do so after the thing is enclosed a couple months from now and this series therefore becomes kind of useless without the ability to get inside.
Would I risk trespassing again? I don't know. It would be awfully easy for me to say no, absolutely not right now, but ask me again after I've stood in front of an open gate with nobody around. The two times I did it were crimes of opportunity, not premeditation. There was no opportunity this time around, as this mid-day lap around the perimeter following Tuesday's jersey unveiling saw plenty of activity on and around the arena's skeleton.
Here is the webcam from the time of the visit (also, as usual, click any photo in this post for the gallery view with larger versions of everything):
We're pretty close to getting some of the brick exterior in place, from the look of things.
First up among my photos is the main entrance, which is quickly becoming my favorite view. It's probably the closest one can (legally) get, so combine that with the obvious significance of this particular part of the structure, and there you go.
If anyone has any clue what this next thing is, feel free to let me know. It's maybe 15 feet removed from the rest of the arena - according to the PIA renderings, the main entrance will have a vestibule that projects outward from the arena, so it's possibly related to that, but how?
Continuing down that side, it's still possible to see all the way through to what will be the windows on the opposite side.
Work on the community rink is finally catching up with the main arena, as you can see in these next two photos.
Looking back towards the main arena shows that the seating bowl has taken shape quite rapidly. In fact, about half of the seating sections are now in place.
Going back by the tennis courts offers maybe the best wide-angle look, although the growing jungle of steel, particularly from the community rink, is quickly obscuring the view.
Of course, the construction entrance off of University Drive is also a good opportunity to get a look without the fence in the way.
And two final shots to complete the loop:
So what's next? Amazingly, if the project keeps close to schedule, it will be drastically further along even by October 12th, the date of the first NCAA home game in Penn State history (and probably the next time I'll do this). We're talking some of the exterior, a finally-closed arena bowl, and substantial progress on getting the whole thing under cover for the winter. Can't wait to see it!
The second picture is the pre-construction mock-up. Its a full-size representation of the proposed construction details and possibly judge appearance of the building.
ReplyDeleteOur firm is working on Pegula, we helped with some of the install.
That makes perfect sense...thanks! It had been bothering me for a while!
DeleteWhy don't you ask them for a tour?
ReplyDeleteInterim Valuation Certificates Negotiate and agree the Final Account figure with the POST-CONTRACT in Dubai, Sharjah,, Kuwait, Qatar, Bahrain, Oman, KSA Final Valuation Certificate. Tender documents are prepared and submitted to the Engineer to issue to approved Tenderers.
ReplyDeletePreparation of Interim Valuation Certificates :
Usually, on a monthly basis, following a site visit to ascertain the progress of Works at site, an Interim Valuation is submitted to enable the Engineer to issue the Interim Payment Certificate.
Pricing of Variations :
The contractual entitlement and cost implications, if any, are determined and recommendations made to the Engineer to enable him to obtain approval from the Client and issue the Engineer’s Instructions.
Nominated Sub-contracts :
For sections of Works, where the Client is to nominate a Subcontractor, the Tender documents are prepared and submitted to the Engineer to issue to approved Tenderers. On receipt, a detailed review is carried out and our recommendations are given to the Engineer / Client for final decision and appointment.
Site Progress / Design Team Meetings :
The Quantity Surveyor will attend the progress meetings as well as the design team meetings.
Cost Report :
On a quarterly basis, a Cost Report is submitted which will clearly indicate
• Work done to-date
• Outstanding Work
• Agreement
• Variations to Contract
• Form of Tender
• Additional Works
• Possible Additions / Omissions to the Contract
• Anticipated Final Cost
This Report will enable cost control and facilitate any corrective measures required to ensure that the project costs remains within budget.
Contract correspondence :
Assist the Engineer in contractual correspondences to ensure the smooth administration of the Works, as per the signed Contract Documents.
Final Account :
Negotiate and agree the Final Account figure with the Contractor and submit the same to Engineer for issue of Final Valuation Certificate.